Estimated timelines are:
| Step | Estimated Time |
| Plan Review | Up to 4 weeks |
| Engineering/Staking | Up to 3 weeks |
| Accounting | Up to 3 weeks |
| Construction (if required) | Up to 4 weeks |
| Metering | Up to 4 weeks |
| Billing & Permission to Operate | Final step |
Overall, projects may take up to 18 weeks from the opening of the service order to receive Permission to Operate, depending on project complexity and whether additional construction is required.