Estimated timelines are:

Step Estimated Time
Plan Review Up to 4 weeks
Engineering/Staking Up to 3 weeks
Accounting Up to 3 weeks
Construction (if required) Up to 4 weeks
Metering Up to 4 weeks
Billing & Permission to Operate Final step

Overall, projects may take up to 18 weeks from the opening of the service order to receive Permission to Operate, depending on project complexity and whether additional construction is required.