What documents are required with my DG application?
With the application, you will need to submit:
Completed DG Interconnection Application available online here
Signed DG Policy Acknowledgment
Complete solar design package
Equipment specification (data) sheets
All required documents should be submitted electronically as labeled PDF files.
What should be included in the solar design package?
Your design package should include:
Site plan with electric locations
Three-line electrical diagram
Approved jurisdictional permits
Electrical equipment details
Production meter location
AC disconnect
Existing electrical panel information
Solar equipment specifications
Battery or generator information (if applicable)
Plans must clearly identify existing and new equipment and be approved by the appropriate Authority Having Jurisdiction (AHJ) before being submitted to VEA.
Here are some examples of specification sheets needed:
Diagram Examples
Three-Line Drawing Example
Do I need to submit manufacturer specification sheets?
Yes.
Manufacturer data sheets must be provided for all applicable equipment, including:
Inverters
Microinverters
Optimizers
Solar panels
Batteries
Generators
AC disconnects
Meter sleeves
Automatic Transfer Switches (ATS)
Any other equipment used in the project
Is there a size limit for residential solar systems?
Yes.
Member-generator systems are limited to less than 25 kW DC total solar capacity per parcel.
Can construction on my project begin once my application is submitted?
No.
Construction may not begin until:
Your application has been approved.
Engineering requirements have been completed.
The final engineering invoice has been paid.
VEA has issued a Permission to Construct letter.
Beginning construction before receiving authorization may delay your project.
How long does the approval process take?
Estimated timelines are:
Step
Estimated Time
Plan Review
Up to 4 weeks
Engineering/Staking
Up to 3 weeks
Accounting
Up to 3 weeks
Construction (if required)
Up to 4 weeks
Metering
Up to 4 weeks
Billing & Permission to Operate
Final step
Overall, projects may take up to 18 weeks from the opening of the service order to receive Permission to Operate, depending on project complexity and whether additional construction is required.
What could delay my project?
v
Common causes of delays include:
Incomplete applications
Missing documentation
Unapproved design plans
Missing signatures
Locked application forms
Payment delays
Additional system construction requirements
Failure to submit final inspection documents
Submitting complete and accurate documentation helps keep your project on schedule.
Common causes of delays include:
Incomplete applications
Missing documentation
Unapproved design plans
Missing signatures
Locked application forms
Payment delays
Additional system construction requirements
Failure to submit final inspection documents
Submitting complete and accurate documentation helps keep your project on schedule.
What is the Interconnection Agreement?
The Agreement for Interconnection of Distributed Generation (AIDG) is a required agreement between the member and VEA.
It is sent with the final engineering invoice and must be signed, notarized, and returned before your net meter can be installed.
When will my net meter be installed?
A net meter cannot be installed until VEA has received:
Signed and notarized Interconnection Agreement
Final county inspection and/or Nevada Housing Division inspection documents (if applicable)
All required approvals
Once everything has been received and verified, the Metering Department will schedule the meter installation.
When can I begin operating my solar system?
Your solar system may only begin operating after VEA issues a Permission to Operate (PTO) letter.
The PTO letter is sent after all inspections, documentation, approvals, and billing requirements have been completed.