Distributed Generation

Woman on telephone
Employees meeting beside trucks
Employee on tower
What documents are required with my DG application?

With the application, you will need to submit:

  • Completed DG Interconnection Application available online here
  • Signed DG Policy Acknowledgment
  • Complete solar design package
  • Equipment specification (data) sheets

All required documents should be submitted electronically as labeled PDF files.

What should be included in the solar design package?

Your design package should include:

  • Site plan with electric locations
  • Three-line electrical diagram
  • Approved jurisdictional permits
  • Electrical equipment details
  • Production meter location
  • AC disconnect
  • Existing electrical panel information
  • Solar equipment specifications
  • Battery or generator information (if applicable)

Plans must clearly identify existing and new equipment and be approved by the appropriate Authority Having Jurisdiction (AHJ) before being submitted to VEA.

Here are some examples of specification sheets needed:

Diagram Examples

Three-Line Drawing Example

Do I need to submit manufacturer specification sheets?

Yes.

Manufacturer data sheets must be provided for all applicable equipment, including:

  • Inverters
  • Microinverters
  • Optimizers
  • Solar panels
  • Batteries
  • Generators
  • AC disconnects
  • Meter sleeves
  • Automatic Transfer Switches (ATS)
  • Any other equipment used in the project
Can construction on my project begin once my application is submitted?

No.

Construction may not begin until:

  • Your application has been approved.
  • Engineering requirements have been completed.
  • The final engineering invoice has been paid.
  • VEA has issued a Permission to Construct letter.

Beginning construction before receiving authorization may delay your project.

How long does the approval process take?

Estimated timelines are:

Step Estimated Time
Plan Review Up to 4 weeks
Engineering/Staking Up to 3 weeks
Accounting Up to 3 weeks
Construction (if required) Up to 4 weeks
Metering Up to 4 weeks
Billing & Permission to Operate Final step

Overall, projects may take up to 18 weeks from the opening of the service order to receive Permission to Operate, depending on project complexity and whether additional construction is required.

What could delay my project?

v

Common causes of delays include:

  • Incomplete applications
  • Missing documentation
  • Unapproved design plans
  • Missing signatures
  • Locked application forms
  • Payment delays
  • Additional system construction requirements
  • Failure to submit final inspection documents

Submitting complete and accurate documentation helps keep your project on schedule.

Common causes of delays include:

  • Incomplete applications
  • Missing documentation
  • Unapproved design plans
  • Missing signatures
  • Locked application forms
  • Payment delays
  • Additional system construction requirements
  • Failure to submit final inspection documents

Submitting complete and accurate documentation helps keep your project on schedule.

What is the Interconnection Agreement?

The Agreement for Interconnection of Distributed Generation (AIDG) is a required agreement between the member and VEA.

It is sent with the final engineering invoice and must be signed, notarized, and returned before your net meter can be installed.

When will my net meter be installed?

A net meter cannot be installed until VEA has received:

  • Signed and notarized Interconnection Agreement
  • Final county inspection and/or Nevada Housing Division inspection documents (if applicable)
  • All required approvals

Once everything has been received and verified, the Metering Department will schedule the meter installation.

When can I begin operating my solar system?

Your solar system may only begin operating after VEA issues a Permission to Operate (PTO) letter.

The PTO letter is sent after all inspections, documentation, approvals, and billing requirements have been completed.